Copper Mountain Mining ( OTCPK:CPPMF ) +13.1% in Wednesday's trading after unveiling a revised life of mine plan that supports mill expansion of its Copper Mountain mining project in British Columbia to 65K tons/day from 45K tons/per day over a 32-year mine life.
The revised life of mine plan also results in robust economics of $1.24B in after-tax net present value at 8% discount, up from its previous estimate of $1B.
The initial capital cost required to increase throughput to 65K tons/day is estimated at $237M.
The miner will need to show a few quarters of improved operations before the market has confidence in the new mine plans, National Bank analysts said.
Copper Mountain Mining ( OTCPK:CPPMF ) "appears undervalued in the mining space but needs strong copper prices to really pay off," R. Paul Drake writes in a bullish analysis posted recently on Seeking Alpha .
For further details see:
Copper Mountain climbs on expanded mining plans, longer mine life