2023-05-11 08:48:50 ET
-
Infrastructure firm Granite ( NYSE: GVA ) said Thursday it got a $65 million preconstruction contract for Parks Highway MP 319-325 in Alaska.
-
The project will be in collaboration with Alaska DOT & PF and its designer, Michael Baker International.
-
The preconstruction services phase will run from early 2023 through summer 2025 to accommodate right-of-way acquisition, permitting, and design completion.
-
The construction phase is expected to begin in the fall of 2025 and finish within the 2027 construction season.
For further details see:
Granite secures $65M preconstruction contract to improve Parks Highway in Alaska